PBOT Accelerates Cully Road Projects Despite Water Line Delays
Excavation begins on NE 68th Avenue next week, while NE 73rd Avenue waits for water bureau work to clear the way.
By Olivia Barnes ·

Drivers and residents in Portland's Cully neighborhood will see a change in the pace of street repairs next week. The Portland Bureau of Transportation plans to start digging on NE 68th Avenue between NE Sumner and NE Going Streets on Monday, November 9. This work is moving faster than the original schedule indicated. Crews also aim to begin rebuilding the roadway on NE Going Street between NE 62nd and NE 72nd Avenues in mid-November.
The project has been underway since July, with PBOT estimating a two-year timeline for completion. The work involves paving gravel streets, installing stormwater drainage, adding curbs and gutters, and improving lighting and planting. Construction moves through the neighborhood in phases to minimize disruption to daily travel.
Not all sections are on track. Roadwork on NE 73rd Avenue, specifically between NE Killingsworth and NE Wygant, has stalled. The delay stems from unexpected tasks by the Portland Water Bureau. Water line work must finish before crews can start on sidewalks. PBOT hopes to resume construction on that stretch in mid-November.
A specific paving day is set for Monday, November 23. From 7 a.m. to 5 p.m., contractors will pave segments of NE 66th Avenue between NE Prescott and NE Going, as well as between NE Wygant and NE Sumner. They will also pave NE 68th Avenue between NE Going and NE Sumner. Drivers must clear their vehicles from these roads by 7 a.m. and may return at 5 p.m., provided the weather cooperates.
The schedule remains fluid. PBOT notes that dates are subject to change as crews balance multiple priorities and weather conditions. The full project roadmap includes work on NE 62nd, 64th, 66th, 70th, 73rd, and 72nd Avenues, as well as NE Going and NE Alberta Streets. Most roadway construction is scheduled to run from late 2026 through early 2028.
Safety changes are coming to NE 72nd Avenue. PBOT will install left turn restrictions on NE Sandy Boulevard and NE Fremont Street. This limits vehicle movements and encourages through traffic to stay on main streets. A new multiuse path will also connect NE Prescott and NE Killingsworth Streets. This path provides dedicated, separated space for walking, biking, and rolling.
These design elements stem from community engagement sessions held in 2020 and 2021. The project is part of the 70s Greenway: Cully Connector Project. It aims to fill a gap in the neighborhood greenway network, making local streets safer and calmer for non-vehicle users.
Property owners have specific responsibilities during and after construction. New sidewalks carry a two-year warranty for material defects. Owners must keep sidewalks clear of leaves and snow. Tree branches extending over sidewalks must stay at least seven and a half feet high, while branches over roadways must be at least 11 feet high.
The public right-of-way includes areas that may currently look private but are city-managed space. PBOT may use these areas for streets and sidewalks, including trimming hedges that encroach on public land. Contractors will not enter private property without advance notice. For questions, residents can contact PBOT Capital Project Manager Sarah Copland-Pullman at 503-865-6046.