Cooper Landing bypass project hits key milestones
Engineers confirm a new bridge is the highest road span in Alaska, while crews continue moving millions of cubic yards of rock toward a 2030 completion.
By Olga Paredes ·

Heavy machinery roared across the Kenai Peninsula this fall as the Cooper Landing bypass project reached critical engineering milestones. The new highway will eventually bypass the town to the north, routing Sterling Highway traffic away from the narrow, winding route that currently crosses the Kenai River twice. Construction crews are moving at a pace that project leaders describe as rarely seen in Alaska, inching toward a completion date estimated for 2030.
Bryan Gallagher, project superintendent for QAP, the general contractor for the roadway, noted the scale of the excavation work. A typical major road project in the state involves removing less than one million cubic yards of material. This project is expected to total close to 6.5 million cubic yards. Gallagher said he will likely never see a construction effort of this magnitude again in his career.
The centerpiece of the project is a bridge over Juneau Creek that engineers have confirmed as the highest road bridge in Alaska. In September, a project engineer measured the drop from the bridge deck to the creek at 291 feet. While a railroad bridge elsewhere in the state is slightly higher, the new structure holds the record for road traffic. Jonathan Tymick, project manager for the state Department of Transportation & Public Facilities, called the project generational.
The bridge was not built over the canyon. Instead, Traylor Brothers Inc., the partner in the joint venture, constructed the structure on the ground nearby. In the summer, crews pushed the bridge into position over the water in a process known as launching. The effort took eight days and involved four large rams moving the structure in 10-foot increments on heavy rollers. At 928 feet, it is the longest launched bridge in the United States, according to Tymick.
The logistical challenge of the bridge was immense. Forty-five steel girders, each between 90 and 120 feet long, were fabricated in Arizona. They were trucked to California, barged to Seward, and then hauled to the job site. Tymick said shipping the girders alone cost $9 million. The completed bridge contains nearly 7 million pounds of structural steel and 4,700 cubic yards of concrete. Bridget Monahan, project manager for Traylor Brothers, said the final pushes were quiet and ended with a collective sigh of relief from the crew.
Costs for the project have risen substantially since early estimates. After the route was selected in 2018, reports pegged the cost at about $375 million. The state’s most recent fact sheet estimates a total of $832.6 million. Tymick said that figure includes a buffer for funding uncertainty that could extend the timeline. He noted that the bridge cost alone has jumped from an initial estimate of $40 million to about $160 million, largely due to unexpected groundwater issues and the need to build the structure higher to accommodate pedestrian trails.
Archaeological work continues in parallel with the heavy construction. The National Historic Preservation Act requires federally funded projects to assess impacts on historic sites. A team from HDR is currently searching for thermal features, such as fire-affected rocks, to help date the area. Aurora Whitesell, a cultural resources specialist, said the team is looking for data that can provide a timeline for human presence in the region. The work is being conducted in coordination with the Kenaitze Indian Tribe and the U.S. Forest Service.
Joel Isaak, operations director for the Kenaitze Tribe, said the selected route eliminates construction in the densest areas of cultural impact. The tribe had opposed other options that would have cut through significant archaeological zones. Isaak said the ongoing excavations are helping to align Western science with traditional oral histories regarding the area’s importance for hunting and fishing.
The new highway will include a pedestrian pathway, eight wildlife crossings, and improved drainage. It will also feature a rebuilt parking lot at the Resurrection Pass Trailhead. The existing highway, built in the 1940s and 1950s, has limited sight lines and insufficient room for passing. A 2018 crash analysis found 303 crashes on the current route between 2000 and 2009, five of which were fatal. The new design aims to reduce those crashes by approximately 70%.